initial ideas-to be completed by Malcolm Pocock- done on 3rd November

Pitch-to be completed by Holly Paterson, Ollie Woodward and Malcolm Pocock- done 14th November 2014

Pitch feedback- to be completed by Holly Paterson, Ollie Woodward and Malcolm Pocock- done on 21st November 2014

Story board/Animatic- to be completed by Holly Paterson - done on 28th November2014

Shot list- to be completed by Holly Paterson- done on 26th November 2014

Shot schedule- to be completed by Ollie Woodward- will be done by 12th December 2014

script- to be completed by Ollie Woodward and Malcolm Pocock- will be done by 12th December 2014

Equipment list- to be completed by Holly Paterson- done on 3rd December 2014

Costumes,props,makeup- to be completed by Holly Paterson- will be done by 13th December 2014

Location Shots- to be completed by Ollie Woodward- done on 24th November 2014

Call sheet- to be completed by Ollie Woodward- by  5th December

Risk Assessment- completed by Holly Paterson, Ollie Woodward and Malcolm Pocock- done by 20th November 2014

Music/sound- will be completed by Holly Paterson- will be done by 15th December 2014

Done by Ollie